Prep work for the additional turn lanes...
"33rd and Broadway
This project will provide for dual southbound and westbound left turn lanes, a single eastbound, westbound and southbound right turn lane. The entire intersection will be reconstructed in concrete pavement. Signal light modifications will accommodate the changes in lane configurations.
This project is part of the 2000 Sales Tax Improvements. The estimated construction cost is $4,936,296.62. The funding split is 60% Federal funds and 40% City funds. The anticipated start date is summer/fall of 2014.
Update: Utility companies will begin to relocate their lines in February 2014 to accommodate the roadway construction."