Traffic Advisory — SH-74 traffic will move to temporary alignment between Memorial Rd., 164th St.
SH-74 traffic will shift to the recently paved west frontage road between Memorial Rd. and N.W. 164th St. on Wednesday afternoon. Shifting traffic to the west allows contractor Haskell Lemon Construction Co. to begin working on the new northbound and southbound lanes of SH-74.
The widening project will reconstruct SH-74 from two lanes to a four-lane divided highway from just north of Memorial Rd. to just north of N.W. 164th St. Also being added in the widening are frontage roads on the east and west sides of the highway.
Drivers are cautioned to remain alert as the changes take effect this week and to plan for extra time while traveling this section of the corridor.
Access from SH-74 to a row of businesses and private entities on the east side of the highway from Memorial Rd. north to N.W. 150th St. will be limited for the next four months. Northbound traffic will be able to access the area from the frontage road, but will not be able to exit back to southbound SH-74. The detour will be Parkway Commons Dr. to Memorial Rd. or to N.W. 150th St.
This $34 million project is the third phase in widening the SH-74 corridor from Memorial Rd. north to Waterloo Rd. Completion of this phase is expected in late spring 2016. The fourth and final phase to four lane SH-74 is scheduled for 2018 from north of N.W. 164th St. to N.W. 206th St. (Covell Rd.).