The renderings don't look that urban at all..
The renderings don't look that urban at all..
The overgrowth of trees to the south of the property, where the parking garage is going to be, needs to be trimmed back.
Let's start with this: There are 2 renderings of the Aloft in this thread, which one is correct? I simply think one is urban, and the other one is not.
Well, the design with the white aLoft is what is being built... The problem with your analysis remains. Both designs were urban, but I could see how you could be mistaken by the first design because it did not clearly show the location of the building to the street. While there are two designs, they were functionally the same.
I concur. I like the changes made in the new rendering. It's going to be a great addition to an urban neighborhood (it feels good to say that).
Yeah, doesn't happen very often..
From Metro:
is it me, or is this project moving really slow?
This. I understand that it's an insanely tedious process to get a project started, but damn... They are moving at an absurdly slow pace.
For not being huge, this is a pretty complicated project.
I suspect they will start to pick up the pace now that most the foundation work is in place.
Level was entirely stick built, with the exception of the parking garage. This is all poured concrete and rebar. And, if you actually look at the structure as it stands, it's not just four walls and level, as noted above. They're working there every day.
I thought I would offer some insight from a civil engineering educational background, hope this answers some previous questions about the pace of the building's construction. I referenced the University of Memphis Department of Civil Engineering below:
During the first week to 10 days of curing it is important that the concrete not be permitted to freeze or dry out because either of these, occurrences would be very detrimental to the strength development of the concrete. Theoretically, if kept in a moist environment, concrete will gain strength forever, however, in practical terms, about 90% of its strength is gained in the first 28 days.
Aloft's foundation was placed in the beginning of November 2011. Depending upon the time line of construction events they may be a little behind, but not by a considerable amount.
On most of my projects in Vegas, once the podium was poured, they were pouring one to one and a half floors per week.
There are currently 1 users browsing this thread. (0 members and 1 guests)
Bookmarks