I know they didn't have funding...that wasn't my question. My question was why not do one side of the interchange at a time instead of doing it this way where it's part of the whole interchange. For example, only do the full westbound side and leave eastbound for later. Or do one corner of it with site prep/etc for the others. It's extremely unusual that they would have released this in a way to do only the structural piers and then wait for the next phase.
Almost like stopping building the capital dome because you ran out of money.
Unless I'm missing something, that interchange today doesn't seem that busy either. With 244 so close, it seems like it's not really such a bottleneck. If we're fighting over funds for interchanges, 240/35 in OKC is about 100 times more busy and we're struggling to get ODOT to fund that one to completion.