Looks like it is delayed again. this time it has a April 2024 construction let date
image_2023-09-09_060947583.jpg
https://spotlight-okdot.hub.arcgis.c...4fb982/explore
ODOT hasn't updated the ArcGIS pages since June. The latest docs have it going out for bid in October (page8):
https://oklahoma.gov/content/dam/ok/...202308-aug.pdf
I wonder if there's any appetite to square up the whole city so there's less back and forth business going on with the border. I'm thinking the OKC folks may not want to though.
In Moore, we can't seem to pass the whole recycle thing, so they'd lose that. And it's not as though the surrounding OKC area is struggling in terms of services being provided. I think it would be a hard sell to convince the residents to make the move in those areas, honestly.
Does this project still have a June start date?
I saw some Is dirt work going on West of the tracks and between fourth and main?
Railroad related delays. Something to do with the railroad needing permission from Amtrack to cross the temp track at a certain speed. Now its September.
UPDATE:
*Originally scheduled for an April '24 letting, BNSF is waiting on approval from Amtrak to lower the speed on the shoofly that will be needed during construction. This, coupled with the utility relocation still ongoing, required an extension to the letting date of September 2024. Once the contract is awarded, construction typically begins after 90 days.
I really thought they would have the buildings bought out and dozed by now that they need cleared. It doesn't look like anyone has done anything.
As of 6/26, it was still on the Tentative September bid opening list
They already have the ROW they need. There is a heat and air company that is losing their front entrance, looks like they already built a new parking lot to the side of their building. Sharkey's Scuba and a barber shop are going to be the most affected. I don't see how they can survive without an entrance off of 4th street. Across the street is the Moore Public Schools supply warehouse which has plenty of entrances off of 4th street.