Phase 4a was just completed - new rail bridge. We are currently in Phase 7. While Phase 2a has been completed for several years.
that phasing map is outdated. Catch22 Explained it well and perhaps we could see future phases expedited if OkDOT gets more funding which is possible if Oklahoma gets its budget situation more solid. OkDOT in the past has moved projects up forward and we'll know more in September or October when they release their update of the 7yr plan.
I believe the bridge over I-44 is currently scheduled to begin in 2019, but as I said, there could be a possibility they move it up, but I'm not holding my breath.
The next two phases are penciled in to be let in November. If this date holds, it will only be a couple of months between actual construction. There is light at the end of the tunnel. Hopefully that light isn't an oil crash and a major decline in Oklahoma's economy.
This current phase won't even be done until the fall, so I don't see them starting the new I-235 bridge any earlier than 2019. Same thing with the last phase, they are going to want to finish the main interchange structure first before working on Lincoln/I-44/NB 235 ramps.
I take the current EB 44 to NB Broadway Extension cloverleaf loop every day, and I can't quite imagine how they could do phase 8 without phase 2B at the same time.
I also can't really imagine how I'm going to get to work without going a completely different route for a while, but that is a separate question.
ODOT just posted on Facebook that the 50th St bridge over I235 is now open.
Yes, 50th Street is open:
Side topic and random but is there a city system map that shows all the underground waterways? I had a rental house at 36th and Francis just SW of here with a drainage outlet on the north side of the street. I have no idea where the inlet is (if there even is one). Same with the one that pops up in Edgemere park.
50th Street is finally open??? :::doing a happy dance::: I work on 48th just west of Lincoln and this has made post office runs and lunch runs so difficult. This is great news!! I may have to go to the post office this afternoon just because it isn't a 15 minute trip anymore!
Overhead signage is going up and you can see them moving fast on the southbound entrance ramp from 50th.
They have also made good progress on the SB outer lanes and the they have moved all the dirt where the NB outer lanes will go.
Decorative retaining wall is going up on the east side. Sound barrier wall is almost done on the west side.
The really need to wrap up all of this.
The big projects are done and not it's just a matter of paving and some finishing touches.
I was wondering about that myself.
I believe the intention is where the tunnel boring machine was lowered down. There’s a large drainage conduit that drains north to the Deep Fork to alleviate the issues that were present under the old RR bridge. The slopes were stabilized with a soil nail wall, and that void is being built up with a mechanically stabilized earth wall.
OH! Didn't catch that. But still....
Southbound was shifted onto new payment last night. This weekend, Northbound will be shifted to the temp lanes southbound use to occupy . Then all of permanent northbound lanes will be built. It will be nice when northbound isn't closed due to flooding.