Following approval of the Master Plan, the Downtown Public Park will be designed and constructed in three
phases, similar to the outline provided in the original MAPS 3 Implementation Plan. Phase 1 will include the
Great Lawn and Promontory, stage, Boulevard Gardens, and temporary Robinson Plaza, to create an immediate
iconic destination and major downtown performance/event venue. Phase 2 will include the balance of the Upper Park
improvements (Union Station improvements are not included in the MAPS 3 budget).
Phase 3 will include all of the
Lower Park improvements to SW 15th Street (river-edge park improvements are not included in the MAPS 3 budget).
It is anticipated that construction of Phase 1 will be completed in Summer/Fall 2015, construction of Phase 2 will be
completed in Winter 2018-19, and
Phase 3 will be completed Winter 2020-21. Park Construction has already begun in
terms of the Upper Park site demolition and preparation, and will be ongoing, with only minor gaps, until completion of
the Lower Park in 2020-21. Park implementation delays could potentially result from land acquisition/assembly obstacles,
hazardous materials remediation, major utility relocation issues, lack of coordination with off-site improvements (such
as the new Downtown Convention Center or the Boulevard), significant changes in scopes of work, or other unforeseen
circumstances.